On August 25th, Oncor filed its direct testimony in Docket No. 36995. The testimony was provided by four witnesses, each supporting sections of the application. Larry Reiter, an Oncor Regional Transmission Planning Manager, submitted testimony addressing ERCOT’s recommendation regarding the proposed transmission line, the adequacy of existing service, the need for additional service, how the […]
36995
Oncor Files CCN Application for Bell, Milam, and Robertson Counties
PUC Docket No. 36995 Oncor filed its application on May 22, 2009, requesting approval to construct a proposed 345 kV transmission line in Bell, Milam and Robertson Counties, Texas. The project will be approximately 41 miles long and is estimated to be energized in May 2011. The proposed transmission line will connect the new Oncor […]