Electric Transmission Texas, LLC (ETT) filed on September 11, 2009, in Docket No. 37547 an application for CCN authority to alleviate uncertainty created by the Travis County District Court’s reversal of the Commission’s December 2007 grant of a transmission-only CCN to ETT. After the District Court issued its judgment, the Legislature enacted House Bill 3309, […]
ett
New Intervention Deadline Set for ETT’s Uvalde and Medina CCN Application
Docket No. 36978 On August 31st, the Administrative Law Judge issued Order No. 7, requiring ETT to send by September 3rd a revised notice to affected property owners in Uvalde and Medina Counties. The new intervention deadline is October 19, 2009.
ETT Files CCN Application for 138 kV Transmission Line in Uvalde and Medina Counties
PUC Docket No. 36978 Electric Transmission Texas LLC (“ETT”) filed its application on July 10, 2009, requesting approval to construct a proposed 138 kV transmission line in Uvalde and Medina Counties, Texas. The project will be located between Uvalde and Castroville and will require approximately 70 miles of new circuits. It is estimated to be energized in […]