Oncor

Oncor files 3 West Texas CREZ CCN applications

September 17, 2009 by Brad Bayliff

On Sept. 16, 2009, Oncor Electric Delivery Company LLC (Oncor) filed three CCN applications for transmission lines associated with the Texas CREZ projects. Docket No. 37407 – Application for the Tonkawa-Sweetwater East-Central Bluff 345 kV CREZ Transmission Line in Scurry, Mitchell, Fisher, Nolan, and Taylor Counties Docket No. 37408 – Application for the Riley-Bowman 345 […]

Filed Under: CREZ, Transmission Line Projects Tagged With: 37407, 37408, 37409, Oncor

Oncor Files Sweetwater-Area CREZ CCN Application

September 17, 2009 by Brad Bayliff

On Sept. 16, 2009, Oncor submitted its application for a CCN for a proposed transmission line in Docket No. 37407. The proposed project will consist of two new double-circuit 345 kV transmission lines. The first line will extend from Oncor’s existing Tonkawa Switching Station, located approximately 16.8 miles west/northwest of Sweetwater in Scurry County to […]

Filed Under: CREZ, Transmission Line Projects Tagged With: Oncor

ALJ Finds Oncor’s Collin Co. Application and Notice Deficient

September 13, 2009 by Brad Bayliff

On Sept. 10, in Order No. 2, the ALJ assigned to Oncor’s Collin County application in Docket No. 37232 found Oncor’s application and notice deficient. Oncor previously responded that it would supplement its application and notice. The intervention deadline is extended for 45 days after the supplemental notice is sent to directly affected landowners, municipalities, […]

Filed Under: CREZ, Transmission Line Projects Tagged With: Oncor

Staff Identifies Deficiencies in Oncor’s Collin Co. CCN Application

September 9, 2009 by Brad Bayliff

Commission Staff filed on September 4th its recommendation in Docket No. 37232 on the sufficiency of the application and notice and addressed other procedural matters. The recommendation identified one deficiency in the application and eight deficiencies in Oncor’s notices to landowners. The application was found to be materially deficient in that it failed to provide […]

Filed Under: CREZ, Transmission Line Projects Tagged With: Oncor

Oncor Files Response to Staff’s Recommendation in Collin Co. CCN Application

September 9, 2009 by Brad Bayliff

On September 9th, Oncor filed its response to the Commission Staff’s recommendation on the sufficiency of its application and notice in Docket No. 37232, Oncor’s application for a proposed 138 kV transmission line in Collin County. In its filing, Staff recommended that the application be found deficient because it did not provide sufficient detail regarding parks […]

Filed Under: CREZ, Transmission Line Projects Tagged With: Oncor

Hearing Date Set for Oncor’s CREZ CCN Application for Jack, Parker and Wise Counties

September 3, 2009 by Brad Bayliff

The administrative law judge (ALJ) in Docket No. 37119, Oncor’s application for a CREZ transmission line in Jack, Parker, and Wise counties, issued Order No. 5, which sets the dates for the hearing on the merits and a briefing schedule. The hearing on the merits of the application is set for October 8-9. Initial briefs […]

Filed Under: CREZ, Transmission Line Projects Tagged With: Oncor

Oncor Requests Dockets for Three CREZ Transmission Lines

August 28, 2009 by Brad Bayliff

Oncor Electric Delivery Company LLC requested that the Public Utility Commission of Texas open three CCN dockets so Oncor may file applications to amend its CCN for proposed CREZ transmission lines. Docket No. 37407 – Oncor’s Application for a Proposed CREZ 345 kV Transmission Line in Scurry, Mitchell, Fisher, Nolan and Taylor Counties Docket No. 37408 […]

Filed Under: CREZ, Transmission Line Projects Tagged With: Oncor

Oncor Files Direct Testimony in Docket No. 36995

August 26, 2009 by Brad Bayliff

On August 25th, Oncor filed its direct testimony in Docket No. 36995. The testimony was provided by four witnesses, each supporting sections of the application. Larry Reiter, an Oncor Regional Transmission Planning Manager, submitted testimony addressing ERCOT’s recommendation regarding the proposed transmission line, the adequacy of existing service, the need for additional service, how the […]

Filed Under: Transmission Line Projects Tagged With: 36995, Oncor

Oncor Files CCN Application for Collin County

August 10, 2009 by Brad Bayliff

Docket No. 37232 On August 7, 2009, Oncor Electric Delivery Company filed an application for approval of a new 138 kV double-circuit transmission line to be built in Collin County, Texas. The proposed transmission line would connect the new Oncor Parker Maxwell Creek substation located east of the City of Parker to the existing Allen […]

Filed Under: Transmission Line Projects Tagged With: Oncor

Oncor Files CCN Application for Bell, Milam, and Robertson Counties

June 24, 2009 by Brad Bayliff

PUC Docket No. 36995 Oncor filed its application on May 22, 2009, requesting approval to construct a proposed 345 kV transmission line in Bell, Milam and Robertson Counties, Texas. The project will be approximately 41 miles long and is estimated to be energized in May 2011. The proposed transmission line will connect the new Oncor […]

Filed Under: Transmission Line Projects Tagged With: 36995, Oncor

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Go to Next Page »

Primary Sidebar

Are you concerned about a proposed transmission line that may affect your property?

Click here to request a free eBrochure for landowners: “What to do if a proposed transmission line may affect your property”

Call Brad Bayliff

My direct number is (512) 225-0027

Featured FAQ posts

Free eBrochure for landowners

Did you receive a letter from an electric utility? Did a utility notify you your property may be affected by a high voltage electric transmission line the utility intends to construct in your area? Are you looking for information on what to do now? Ask for my free eBrochure for landowners “What to do if […]

Should you intervene?

Are you a Texas landowner concerned about a transmission line proposed to be built near your property? Have you received a letter notifying you that your property may be affected by a new transmission line? Do you want to know your options to protect your rights? Should you intervene? The most important thing! The most […]

More Posts from this Category

Categories

  • Home
  • About
  • Practice Areas
  • Blog
  • FAQs
  • Contact

Copyright © 2012 ‐ 2026 Bayliff Law Firm PLLC - The lawyer you choose makes a difference • Blanco, Texas • All Rights Reserved
Privacy Policy • Disclaimers and Terms of Use
(512) 480-9900